Eager conflict resolution
=========================

Eager conflict resolution (also known as Eager Replication) prevents
conflicts by aborting transactions that conflict with each other with
serializable errors during the COMMIT decision process.

You configure it using :ref:`Commit scopes <Commit scopes>`  as one of the conflict resolution
options for :ref:`Group commit <Group commit>`  .

Usage
-----

To enable Eager conflict resolution, the client needs to switch to a
commit scope, which uses it at session level or for individual
transactions as shown here:

.. code:: sql

   BEGIN;

   SET LOCAL bdr.commit_scope = eager_scope;

   ... other commands possible...

The client can continue to issue a ``COMMIT`` at the end of the
transaction and let PGD manage the two phases:

.. code:: sql

   COMMIT;

In this case, the ``eager_scope`` commit scope is defined something like
this:

.. code:: sql

   SELECT bdr.add_commit_scope(
       commit_scope_name := eager_scope,
       origin_node_group := top_group,
       rule := ALL (top_group) GROUP COMMIT (conflict_resolution = eager, commit_decision = raft) ABORT ON (timeout = 60s),
       wait_for_ready := true
   );

..  note Upgrading?::
   The old `global`  commit scope doesn't exist anymore. The above command creates a scope that's the same as the old `global`  scope with `bdr.global_commit_timeout`  set to `60s` .

The commit scope group for the eager conflict resolution rule can only
be ``ALL`` or ``MAJORITY`` . Where ``ALL`` is used, the
``commit_decision`` setting must also be set to ``raft`` .

Error handling
--------------

Given that PGD manages the transaction, the client needs to check only
the result of the ``COMMIT`` . This is advisable in any case, including
single-node Postgres.

In case of an origin node failure, the remaining nodes eventually (after
at least ``ABORT ON timeout`` ) decide to roll back the globally
prepared transaction. Raft prevents inconsistent commit versus rollback
decisions. However, this requires a majority of connected nodes.
Disconnected nodes keep the transactions prepared to eventually commit
them (or roll back) as needed to reconcile with the majority of nodes
that might have decided and made further progress.

Effects of Eager Replication in general
---------------------------------------

Increased abort rate
^^^^^^^^^^^^^^^^^^^^

With single-node Postgres, or even with PGD in its default asynchronous
replication mode, errors at ``COMMIT`` time are rare. The added
synchronization step due to the use of a commit scope using eager for
conflict resolution also adds a source of errors. Applications need to
be prepared to properly handle such errors (usually by applying a retry
loop).

The rate of aborts depends solely on the workload. Large transactions
changing many rows are much more likely to conflict with other
concurrent transactions.

Effects of MAJORITY and ALL node replication in general
-------------------------------------------------------

Increased commit latency
^^^^^^^^^^^^^^^^^^^^^^^^

Adding a synchronization step due to the use of a commit scope means
more communication between the nodes, resulting in more latency at
commit time. When ALL is used in the commit scope, this also means that
the availability of the system is reduced, since any node going down
causes transactions to fail.

If one or more nodes are lagging behind, the round-trip delay in getting
confirmations can be large, causing high latencies. ALL or MAJORITY node
replication adds roughly two network round trips (to the furthest peer
node in the worst case). Logical standby nodes and nodes still in the
process of joining or catching up aren’t included but eventually receive
changes.

Before a peer node can confirm its local preparation of the transaction,
it also needs to apply it locally. This further adds to the commit
latency, depending on the size of the transaction. This setting is
independent of the ``synchronous_commit`` setting.