Known issues and limitations
============================

Known issues
------------

These are currently known issues in EDB Postgres Distributed
{{version.full}}. These known issues are tracked in PGD’s ticketing
system and are expected to be resolved in a future release.

- Replication of materialized views only works with newly-created
  materialized views. Materialized views that were created before
  upgrading to {{version.full}}.0 do not get replicated after upgrading.
  To prevent this issue, you can do one of the following:

- Before upgrading to PGD {{version.full}}.0., manually create the
  materialized view on each node. - OR

- After upgrading to PGD {{version.full}}.0., drop and create the
  materialized view so that it gets replicated.

- If the resolver for the ``update_origin_change`` conflict is set to
  ``skip`` , ``synchronous_commit=remote_apply`` is used, and concurrent
  updates of the same row are repeatedly applied on two different nodes,
  then one of the update statements might hang due to a deadlock with
  the PGD writer. As mentioned in `Conflicts <https://www.enterprisedb.com/docs/pgd/latest/reference/conflict-management/conflicts/>`_  , ``skip`` isn’t the
  default resolver for the ``update_origin_change`` conflict, and this
  combination isn’t intended to be used in production. It discards one
  of the two conflicting updates based on the order of arrival on that
  node, which is likely to cause a divergent cluster. In the rare
  situation that you do choose to use the ``skip`` conflict resolver,
  note the issue with the use of the ``remote_apply`` mode.

- The Decoding Worker feature doesn’t work with CAMO/Eager/Group Commit.
  Installations using CAMO/Eager/Group Commit must keep
  ``enable_wal_decoder`` disabled.

- Lag Control doesn’t adjust commit delay in any way on a fully isolated
  node, that’s in case all other nodes are unreachable or not
  operational. As soon as at least one node connects, replication Lag
  Control picks up its work and adjusts the PGD commit delay again.

- For time-based Lag Control, PGD currently uses the lag time, measured
  by commit timestamps, rather than the estimated catch up time that’s
  based on historic apply rates.

- Changing the CAMO partners in a CAMO pair isn’t currently possible.
  It’s possible only to add or remove a pair. Adding or removing a pair
  doesn’t require a restart of Postgres or even a reload of the
  configuration.

- Group Commit can’t be combined with `CAMO <https://www.enterprisedb.com/docs/pgd/latest/reference/commit-scopes/camo/>`_  .

- Transactions using Eager Replication can’t yet execute DDL. The
  TRUNCATE command is allowed.

- Parallel Apply isn’t currently supported in combination with Group
  Commit. Make sure to disable it when using Group Commit by either (a)
  Setting ``num_writers`` to 1 for the node group using `bdr.alter_node_group_option <https://www.enterprisedb.com/docs/pgd/latest/reference/tables-views-functions/nodes-management-interfaces/#bdralter_node_group_option>`_  or
  (b) using the GUC `bdr.writers_per_subscription <https://www.enterprisedb.com/docs/pgd/latest/reference/tables-views-functions/pgd-settings#bdrwriters_per_subscription>`_  . See :ref:`Configuration of generic replication <Replication>`  .

- There currently is no protection against altering or removing a commit
  scope. Running transactions in a commit scope that’s concurrently
  being altered or removed can lead to the transaction blocking or
  replication stalling completely due to an error on the downstream node
  attempting to apply the transaction. Make sure that any transactions
  using a specific commit scope have finished before altering or
  removing it.

- The `PGD CLI <https://www.enterprisedb.com/docs/pgd/latest/reference/cli>`_  can return stale data on the state of the cluster if
  it’s still connecting to nodes that were previously parted from the
  cluster. Edit the :ref:`pgd-cli-config.yml <Configuring Connection Manager>`  file, or change your :ref:`--dsn <Configuring Connection Manager>` 
  settings to ensure only active nodes in the cluster are listed for
  connection.

To modify a commit scope safely, use `bdr.alter_commit_scope <https://www.enterprisedb.com/docs/pgd/latest/reference/tables-views-functions/functions#bdralter_commit_scope>`_  .

- DDL run in serializable transactions can face the error:
  ``ERROR: could not serialize access due to read/write dependencies among transactions``
  . A workaround is to run the DDL outside serializable transactions.

- The EDB Postgres Advanced Server 17 data type :ref:`BFILE <Monitoring through SQL>`  is not
  currently supported. This is due to ``BFILE`` being a file reference
  that is stored in the database, and the file itself is stored outside
  the database and not replicated.

Limitations
-----------

Take these EDB Postgres Distributed (PGD) design limitations into
account when planning your deployment.

Nodes
^^^^^

- PGD can run hundreds of nodes, assuming adequate hardware and network.
  However, for mesh-based deployments, we generally don’t recommend
  running more than 48 nodes in one cluster. If you need extra read
  scalability beyond the 48-node limit, you can add subscriber-only
  nodes without adding connections to the mesh network.

- The minimum recommended number of nodes in a group is three to provide
  fault tolerance for PGD’s consensus mechanism. With just two nodes,
  consensus would fail if one of the nodes were unresponsive. Consensus
  is required for some PGD operations, such as distributed sequence
  generation. For more information about the consensus mechanism used by
  EDB Postgres Distributed, see :ref:`Architecture overview <Architecture overview>`  .

Multiple databases on single instances
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Support for using PGD for multiple databases on the same Postgres
instance is **deprecated** beginning with PGD 5 and will no longer be
supported with PGD 6. As we extend the capabilities of the product, the
added complexity introduced operationally and functionally is no longer
viable in a multi-database design.

It’s best practice and we recommend that you configure only one database
per PGD instance.

The tooling such as the CLI and Connection Manager currently codify that
recommendation.

While it’s still possible to host up to 10 databases in a single
instance, doing so incurs many immediate risks and current limitations:

- If PGD configuration changes are needed, you must execute
  administrative commands for each database. Doing so increases the risk
  for potential inconsistencies and errors.

- You must monitor each database separately, adding overhead.

- Connection Manager works at the Postgres instance level, not at the
  database level, meaning the leader node is the same for all databases.

- Each additional database increases the resource requirements on the
  server. Each one needs its own set of worker processes maintaining
  replication, for example, logical workers, WAL senders, and WAL
  receivers. Each one also needs its own set of connections to other
  instances in the replication cluster. These needs might severely
  impact performance of all databases.

- Synchronous replication methods, for example, CAMO and Group Commit,
  won’t work as expected. Since the Postgres WAL is shared between the
  databases, a synchronous commit confirmation can come from any
  database, not necessarily in the right order of commits.

- CLI integration assumes one database.

Durability options (Group Commit/CAMO)
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

There are various limits on how the PGD durability options work. These
limitations are a product of the interactions between Group Commit and
CAMO, and how they interact with PGD features such as the :ref:`WAL decoder <Decoding worker>` 
and `transaction streaming <https://www.enterprisedb.com/docs/pgd/latest/reference/transaction-streaming/>`_  .

Also, there are limitations on interoperability with legacy synchronous
replication, interoperability with explicit two-phase commit, and
unsupported combinations within commit scope rules.

The following limitations apply to the use of commit scopes and the
various durability options they enable.

General durability limitations
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

- `Legacy synchronous replication <https://www.enterprisedb.com/docs/pgd/latest/reference/commit-scopes/legacy-sync>`_  uses a mechanism for transaction confirmation different from the one used by CAMO, Eager, and Group Commit. The two aren't compatible, so don't use them together. Whenever you use Group Commit, CAMO, or Eager, make sure none of the PGD nodes are configured in `synchronous_standby_names` . 

- Postgres two-phase commit (2PC) transactions (that is, :ref:`PREPARE    TRANSACTION <Monitoring through SQL>` 
  ) can’t be used with CAMO, Group Commit, or Eager because those
  features use two-phase commit underneath.

Group Commit
^^^^^^^^^^^^

`Group Commit <https://www.enterprisedb.com/docs/pgd/latest/reference/commit-scopes/group-commit>`_  enables configurable synchronous commits over nodes in a
group. If you use this feature, take the following limitations into
account:

- Not all DDL can run when you use Group Commit. If you use unsupported
  DDL, a warning is logged, and the transactions commit scope is set to
  local. The only supported DDL operations are:

- Nonconcurrent ``CREATE INDEX``

- Nonconcurrent ``DROP INDEX``

- Nonconcurrent ``REINDEX`` of an individual table or index

- ``CLUSTER`` (of a single relation or index only)

- ``ANALYZE``

- ``TRUNCATE``

- Explicit two-phase commit isn’t supported by Group Commit as it
  already uses two-phase commit.

- Combining different commit decision options in the same transaction or
  combining different conflict resolution options in the same
  transaction isn’t supported.

- Currently, Raft commit decisions are extremely slow, producing very
  low TPS. We recommended using them only with the ``eager`` conflict
  resolution setting to get the Eager All-Node Replication behavior of
  PGD 4 and older.

Eager
^^^^^

`Eager <https://www.enterprisedb.com/docs/pgd/latest/reference/commit-scopes/group-commit/#eager-conflict-resolution>`_  is available through Group Commit. It avoids conflicts by
eagerly aborting transactions that might clash. It’s subject to the same
limitations as Group Commit.

Eager doesn’t allow the ``NOTIFY`` SQL command or the ``pg_notify()``
function. It also doesn’t allow ``LISTEN`` or ``UNLISTEN`` .

CAMO
----

`Commit At Most Once <https://www.enterprisedb.com/docs/pgd/latest/reference/commit-scopes/camo>`_  (CAMO) is a feature that aims to prevent applications
committing more than once. If you use this feature, take these
limitations into account when planning:

- CAMO is designed to query the results of a recently failed COMMIT on
  the origin node. In case of disconnection, the application must
  request the transaction status from the CAMO partner. Ensure that you
  have as little delay as possible after the failure before requesting
  the status. Applications must not rely on CAMO decisions being stored
  for longer than 15 minutes.

- If the application forgets the global identifier assigned, for
  example, as a result of a restart, there’s no easy way to recover it.
  Therefore, we recommend that applications wait for outstanding
  transactions to end before shutting down.

- For the client to apply proper checks, a transaction protected by CAMO
  can’t be a single statement with implicit transaction control. You
  also can’t use CAMO with a transaction-controlling procedure or in a
  ``DO`` block that tries to start or end transactions.

- CAMO resolves commit status but doesn’t resolve pending notifications
  on commit. CAMO doesn’t allow the ``NOTIFY`` SQL command or the
  ``pg_notify()`` function. They also don’t allow ``LISTEN`` or
  ``UNLISTEN`` .

- When replaying changes, CAMO transactions might detect conflicts just
  the same as other transactions. If timestamp-conflict detection is
  used, the CAMO transaction uses the timestamp of the
  prepare-on-the-origin node, which is before the transaction becomes
  visible on the origin node itself.

- CAMO isn’t currently compatible with transaction streaming. Be sure to
  disable transaction streaming when planning to use CAMO. You can
  configure this option globally or in the PGD node group. See
  :ref:`Transaction streaming configuration <Transaction streaming>`  .

- CAMO isn’t currently compatible with decoding worker. Be sure to not
  enable decoding worker when planning to use CAMO. You can configure
  this option in the PGD node group. See :ref:`Decoding worker disabling <Decoding worker>`  .

- Not all DDL can run when you use CAMO. If you use unsupported DDL, a
  warning is logged and the transactions commit scope is set to local
  only. The only supported DDL operations are:

- Nonconcurrent ``CREATE INDEX``

- Nonconcurrent ``DROP INDEX``

- Nonconcurrent ``REINDEX`` of an individual table or index

- ``CLUSTER`` (of a single relation or index only)

- ``ANALYZE``

- ``TRUNCATE``

- Explicit two-phase commit isn’t supported by CAMO as it already uses
  two-phase commit.

- You can combine only CAMO transactions with the ``DEGRADE TO`` clause
  for switching to asynchronous operation in case of lowered
  availability.

Mixed PGD versions
^^^^^^^^^^^^^^^^^^

PGD was developed to :ref:`enable rolling upgrades of PGD <pgd node upgrade>`  by allowing mixed versions of PGD to
operate during the upgrade process. We expect users to run mixed
versions only during upgrades and, once an upgrade starts, that they
complete that upgrade. We don’t support running mixed versions of PGD
except during an upgrade.

Other limitations
^^^^^^^^^^^^^^^^^

This noncomprehensive list includes other limitations that are expected
and are by design. We don’t expect to resolve them in the future.
Consider these limitations when planning your deployment:

- A ``galloc`` sequence might skip some chunks if you create the
  sequence in a rolled back transaction and then create it again with
  the same name. Skipping chunks can also occur if you create and drop
  the sequence when DDL replication isn’t active and then you create it
  again when DDL replication is active. The impact of the problem is
  mild because the sequence guarantees aren’t violated. The sequence
  skips only some initial chunks. Also, as a workaround, you can specify
  the starting value for the sequence as an argument to the
  ``bdr.alter_sequence_set_kind()`` function.